Layout Setup SOP
A. Prior to Show - All Members (AM)
- Insure you have module(s), legs, nuts, bolts, washers, tools,
connector track, 4 2" or 3" C-clamps, skirting, buildings, vehicles,
engines and trains staged in a central location, ready for loading
and transporting to show
B. Pre Show Checklist - Modular Superintendant (MS)
- Get participating module list from members
- Set setup time
- Arrange transportation if needed
- Arrange module layout and track plan
- Designate Command Station and Booster locations
- Designate UTP location
- Assign functional responsibilities for Module and DCC/Electrical
Setup crews
*** Each member is responsible for their own module(s). If a
member cannot be at a particular phase of the show, it is their
responsibility to find a maintainer ***
C. Setup Day - Finish Each Major Step Before Going to Next Step
- Transportation and unloading (AM)
- Unload modules and all other stuff in general location of layout
- Check with MS or track plan for final module location
- Module Setup (AM and Module Crew)
- Setup all modules - NO CONNECTIONS (Track or Electrical)
- Level all modules
- Leveling Procedure - set left and right height to 40"
to top of rail or 39 13/16" to top of roadbed (rail and
tie height is 3/16"). Level module front to back at both
ends. Move to next module.
- Check alignment of modules prior to connection modules
- Module Connection (AM and Module Crew)
- Module setup crews, beginning at Charlie's lift bridge,
begin connecting/clamping modules together
- Ensure smoothe transition between modules
- Do Not Connect Electrical or Connector Track
- After all modules are connected check Charlie's lift bridge
for proper operation
- DCC/Electrical Connection (DCC/Electrical Crew)
- Place Command Station, Boosters and power supplies per
track plan
- Run extension cords to power supplies
- Place district flags and insulated rail joiners for
district separations
- Starting with Command Station district, connect wires to mainline
and power to booster. Test operation.
- Working clockwise from Command Station, connect the next booster
and test operation.
- After all boosters are connected and tested install the UTP's
according to track plan and test operation.
- Track Connection (DCC/Electrical Crew)
- Place and connect connector track, mainline only. Ensure mainline
is double insulated.
- Fix any mismatches in connector track
- Test-run trains on mainline tracks
- Clean mainline
- Place and connect remaining connector tracks
- Clean remaining tracks
- Attach Backdrops (AM)
- Place Structures and Other Scenery Items (AM)
- Attach Skirting and Safety Guards (AM)
- Add Trains (AM)
E. Tear Down
- Remove Trains
- Remove Skirting and Safety Guards
- Remove Structures and Other Scenery Items
- Remove Backdrops
- Remove UTP's
- Remove Command Station and Boosters
- Disconnect all Connector Track
- Separate Modules
- Teardown Modules
- Load Into Vehicles
- Conduct After Action Review
- Go Home and Get Plenty of Rest